Before You Begin Applying for Service
Applicants or their representatives requesting service, should be familiar with PSE&G's specific service characteristics and installation requirements.
- Electric Service: PSE&G's Information & Requirements for Electric Service
- Bulletins:
- (April 23, 2008: View Revised Chapters)
- (November 30, 2006: View Revised Chapters)
- (January 6, 2006: View Revised Chapters)
- Gas Service: General Criteria for Installation of Gas Appliances and Gas Piping
- PSE&G Tariff
- Plant Engineering Policies & Procedures:
- Customer Equipment Requirements for Primary Service (Chapter 3)
- PSE&G General Specifications for a Customer-Owned 26-4-kV Outdoor Substation (Chapter 4)
- PSE&G General Specifications for a Customer-Owned 26-4-kV Metal-Clad Substation (Chapter 5)
- PSE&G General Specifications for a Customer-Owned 69-kV Outdoor Substation (Chapter 6)
- High Voltage Proximity Act
- Uniform Construction Standard
- New Jersey Adminsitrative Code
- Installing New Services
Apply Online /
Construction Service Applications
Ask questions about a new installation of electric and gas services.
click here